By Chad Selweski
@cbsnewsman on Twitter
Macomb County government buildings need $102 million
worth of improvements and upgrades but the county lacks the cash to replace all
that aging infrastructure, and officials would plunge the county budget into
deficits by 2017 if it tried to make all the necessary repairs.
That was the quandary placed before the Board of
Commissioners this week as they contemplated a 5-year list of projects, nearly
all of which were labeled an “immediate priority.”
At the top of the list is repairing and modernizing the
shuttered old County Building in downtown Mount Clemens, which suffered water
and smoke damage during an electrical fire last spring. Officials await a $10
million insurance settlement to help pay for the overhaul.
But the County Building represents just one piece of a
$25 million downtown project that includes substantial upgrades and the
addition of new courtrooms in the Court Building, and the filling out of two
floors that have been left vacant in the Administration Building since it was
opened in 1998.
The capital projects plan also calls for $8 million in
repairs to the county jail and the potential reconstruction of the crumbling parking
structure in Mount Clemens at a price tag of $25 million.
Commissioner Veronica Klinefelt warned that the costs are
so difficult to manage that the political implications for the 13-member board
could be calamitous.
“We’re talking like we’re going to do all of these. But
if we do that, nobody here’s going to have a job fairly soon,” said the
Eastpointe Democrat,  adding that the
projects put out for bid in the next few years should be limited only to those
that we “absolutely, positively have to do.”
But after years of deferrals on basic building
maintenance projects, particularly in 2006-10 when the local economy and
housing market took a dive, few repairs can be set aside.
The tally of 25 projects includes replacement of obsolete
heating/air conditioning units, electrical power systems, sewage disposal,
water mains and boilers.
The four elevators in the Court Building date back to
1969 and the two in the adjacent 13-story County Building were installed in the
early 1970s. As a result, instances of people getting trapped in a
malfunctioning elevator are becoming more common. What’s more, the freight
elevator at the County Building originated in 1932. The overall fix? A $1.3
million replacement plan.
County Finance Director Pete Provenzano opposes municipal
bond sales to pay for any of the $102 million total. He prefers a pay-as-you-go
system, with the county allocating portions of its $83 million accumulated
surplus – the “rainy day” fund – at strategic times over the next five years.
One option presented to the commissioners would feature a
$25 million bond sale that would cost nearly $2 million a year in principal and
interest payments. Provenzano said borrowing to pay for the many renovations is
counterproductive because the end result is the county pays 50 percent more
than if it pays cash.
The separate capital improvements budget is out of date,
with just $15 million set aside for infrastructure needs.
Board Chairman Dave Flynn warned that the 2014-18 capital
improvements plan will involve a “zero sum game,” with some buildings receiving
improvements at the expense of other facilities.
The needed improvements stretch far and wide, from the
Southeast Health Center in St. Clair Shores to the Independence Building at
Freedom Hill County Park in Sterling Heights to the Animal Shelter in Clinton
Township. 
In addition, Lynn Arnott-Bryks, director of Facilities
and Operations, warned at Thursday’s special board meeting that more than $9
million must be budgeted for unanticipated repairs and scheduled maintenance
for parking lots, roofs, walls and sidewalks.
And the 5-year capital plan projects the need for $5
million worth of upgrades in computer equipment and software.
Under the county charter, County Executive Mark Hackel
can create his own priority list and pursue projects in a chronology of his
choosing. But Provenzano said the executive’s office wants the board to “buy
into” a revised capital spending plan so that the commissioners don’t hit the
brakes when they’re asked to approve individual construction contracts.
The trickiest issue may center on what to do about the
six-story Main Street parking structure, built in 1978-79, which has been
crumbling for years. Ongoing maintenance costs $300,000 a year and snow
removal  in January alone hit a price tag
of $121,000. Reconstructing the 600-space structure will cost $25 million.
Demolition would cost just $1 million, but it would leave only enough surface
parking for about 100 vehicles.
The county may seek to negotiate a deal with the city of
Mount Clemens to lease some of the hundreds of city-owned, metered spaces
nearby.
In November, the commissioners were first presented with
an ambitious multi-phase plan to rebuild the parking structure, renovate the
County Building and Court Building, and finish the Administration Building’s
fifth and sixth floors.
The projects would lead to resettling some of the
county’s busiest departments, including the Clerk’s Office, Circuit Court,
Juvenile Court and Friend of the Court. The adjacent Clemens Center and Talmer
Bank administrative building, recently purchased by the county for $1 million,
would also play roles in the reshuffling.
The commissioners have scheduled four more meetings over
the next five weeks to discuss infrastructure issues with the Hackel
administration, with each session featuring a roundtable, work-group format
as was the case on Thursday.